When one of the nation’s largest financial institutions wanted to create a consistent charging experience for employees, they did their homework. The company knew coordinating 350 charging stations simultaneously across 12 locations spanning four time zones would bring operational, physical and logistical challenges. From a constrained urban parking facility in San Francisco to a sprawling campus in Des Moines, each site demanded a different approach while supporting a shared vision: creating consistency across the company’s largest corporate campuses by making reliable EV charging part of the employee experience.
The company turned to McKinstry as its design-build partner to help bring that vision to life.
One Program, Multiple Campuses
Rather than applying the same solution at each location, the project team worked to understand how each site operated and what success looked like for the people who manage it day-to-day. This flexibility allowed the broader program to maintain consistency while adapting to the unique characteristics of each facility.
In San Francisco, available space was at a premium and every square foot mattered. Integrating charging infrastructure into an active parking facility required careful coordination around parking dimensions, daily operations and valet services.
More than 1,800 miles away in Des Moines, the challenge looked different. Space was less constrained, allowing the project team to focus on how charging infrastructure would fit into the broader employee and guest experience. Equipment placement, accessible design, landscaping and sightlines were all considered to ensure the charging stations complemented the campus environment.
Navigating Operational Complexity
Other locations introduced their own complexities. Some campuses housed critical operations, including a data center and cash vault facilities that needed to remain fully operational throughout construction. Shutting down operations was not an option, requiring detailed work plans, extensive coordination with the utility, carefully sequenced schedules and overcommunication between project teams and facility stakeholders.
For Sean Anderson, Project Manager and lead contact for this project, that adaptability was key to the project’s success.
“Every site had different needs,” Anderson said. “We needed to understand how each campus operated and adapt our approach so we could deliver the client’s broader goals without disrupting employees’ work or ongoing operations.”
Building a Consistent Employee Experience
The result was a private nationwide charging network tailored to the unique requirements of a diverse real estate portfolio. More importantly, it turned an ambitious workplace charging initiative into an amenity employees can use every day.
For organizations considering electrification across multiple facilities, the project demonstrates that successful implementation at scale is not about repeating the same design from one site to the next. It is about creating a consistent program while accounting for the characteristics that make each location unique.
Investing in Employees Through Infrastructure
Reflecting on the project, Anderson said the client’s investment stood out not only for its scale, but also for its focus on employees.
“It’s very inspiring that a company invests millions in providing EV charging for their employees,” Anderson said. “It’s a daily reminder that their employer is investing in supporting them, and it adds benefits of coming into the workplace.”
Today, charging infrastructure is in place across a dozen corporate campuses, supporting employees from coast to coast. The program demonstrates how organizations can scale EV charging across diverse facilities while remaining responsive to local operational needs.



Explore Other Projects
Scaling EV Charging Across 12 Corporate Campuses
When one of the nation’s largest financial institutions wanted to create a consistent charging experience for employe…
From Pilot to Districtwide Strategy: Cumberland County Sc…
McKinstry and Cumberland County Schools in Tennessee turned facility data into districtwide strategy, transforming a …
Adams State University Brings First Darcy Geothermal Syst…
Innovative technology reduces land use and cost, expanding access to geothermal energy for communities across Colorad…